Century Mine – Apron Feeder Chain

Scope: The scope of work included the change out of chains and sprockets on the AF-001 Apron Feeder Challenges: There was no manual braking system on AF-001. Specialised tooling was engineered and fabricated to secure the chains while the AF001 was being worked on. A brake disc was attached to the left hand drive motor...

Read More

Wesfarmers Curragh Survey

Scope: Provide volumetric differences of the Process Water and Tailings solids in the Tailings Storage Facility. Raw Data and Graphical Formats are provided on a regular basis. Storage confirmation of onsite mine-affected and clear water holding facilities. Challenges: Pit is 1200m long with access from one end only. Survey must be carried out whilst...

Read More